This part of the PBUUC Web Site will keep people up to date about the December 9 fire in the RE building and our REbuilding plans.
RE build task force annual report This report includes some background material, a timeline of work to date, and cost estimates for upgrades beyond the repairs insurance is paying for. [5/28/04]
CAPITAL CAMPAIGN STATUS: As of 5/26, we had pledges of $183,000, with 100 pledging households to be called in the follow up to Super Sunday.
This section contains bulletins that are more than a week or so old.
[1/12/04] Added more fire department links in media section.
[12/31/03] New Year's message from the Co-Ministers.
[12/11/03]
The Board met in emergency section on Thursday, December 11 to deal with the aftermath of the fire. Key decisions so far; these are really immediate issues only:
[12/13/03]
A mailing is going out from the Board Real Soon Now with far more than this immediate information -- when it is ready a copy will be put here as well.
[12/14/03]
[12/20/03]
[12/23/03]
Religious Education to begin at High Point High School on Jan. 4: On Dec. 17 the Board of Trustees agreed to fund Sunday rental space for our Religious Education program at High Point High School (one mile north on Powder Mill Road), at an estimated $120 for two-hours each week. This will begin on Jan. 4 with a Children's Chapel, which parents and other adults are welcome to attend (and then tour the rented rooms). Meanwhile, temporary Nursery space has been established in the Meeting House at the end of the rest room corridor.
Contents Departing: As of Dec. 23, almost all of the RE Building "contents" that belong to us and are salvagable have been removed for professional cleaning off-site. (Most of the Montessori belongings still remain, but will be removed soon.) The storage "pods" that dot the perimeter of the parking lot will also be gone soon.
Estimates Underway: Our contractor, Belfor USA, is actively detailing estimates of what the re-build will cost AND what code upgrades will be required. They are awaiting the report from a code engineer and predict they will have preliminary figures to us in early January.
[1/3/04]
Added link to PG Gazette story on December 24.
ATTENTION MONTESSORI PARENTS & CHURCH MEMBERS!!!!!!!
PAINT BRANCH MONTESSORI SCHOOL WILL BE IN THE MEETINGHOUSE DURING THE DAY FROM 1/5 TO 1/9; THEY NEED TO HOLD A PUBLIC HEARING BEFORE OCCUPYING THEIR NEW QUARTERS.
TV coverage on NBC4, on Channel 7 -- and on News Channel 8 web site
Story in Wednesday, December 10 Washington Post Metro section
Story in Thursday, December 11 Washington Post Prince George's Weekly section
Story from the PG Gazette December 11; followup on December 24.
Branchville Volunteer Fire Company #11 has a brief note on its current news Web page; it is dated December 9.
Laurel Volunteer Fire Department also responded (page down to December 9 entry "Engine 103 On 2nd Alarm Calverton School Fire" -- they have Real player audio of the call available.
As did the Burtonsville Volunteer Fire Depratment and the Beltsville Volunteer Fire Depratment
Donna Britt Column in December 19 Washington Post Metro Section.
Photos from NBC4 Web site